Turbigo

Press Release. The new combined cycle, with a yield of 57%, will be able to achieve its first parallel by il 31/03/2022, while the completion of trial operation and testing is scheduled for 30/06/2022.

Ansaldo Energia will be in charge of executive design, supply of the AE94.3A gas turbine, generators and step-up transformers, the recovery steam generator, civil construction works, and supply and assembly of electrical and mechanical auxiliary equipment.

Iren will integrate the project with the existing plant to achieve maximum overall flexibility in production, renew a number of components of the existing production plant which have been in service since 2008 to further improve performance, and renew connections with the national electricity grid.

Source: Press Release